COST OF MATERIALS
BEAM:
16 MM D. BAR - 6 pcs. 1,770.00
10 MM D. BAR - 5 pcs. 575.00
12 MM D. BAR – 2 pcs. 336.00
TIE WIRE #16 – 3 kgs. 180.00
POTRLAND CEMENT - 3 bags 624.00
ORD. PLYWOOD ¼ - 2 sheets 500.00
COCO LUMBER 2X2X12 6 pcs. 330.00
COCO LUMBER 2X3X12 3 pcs 225.00
COMMON NAIL #4 3 kgs. 140.00
COMMON NAIL #2 ½ 2 kgs. 140.00
COMMON NAIL #1 ½ 1 kg. 70.00
TOTAL P4,890.00
4,890 / BEAM
15 BEAMS – P73,350.00
STEEL TRUSS:
ANGLE BARS 2X2X¼ 105 pcs. 60,375.00
FLAT BAR 1X1X¼ 25 pcs. 6,250.00
WIELDING ROD WIPWELD 6013 40 kgs. 4,000.00
C-PURLINS 2X2X1/16 52 pcs. 24,700.00
RED OXIDE METAL PRIMER 10 gallons 2,600.00
TOTAL 97,925.00
CONCRETE GUTTER:
12 MM D. BAR 15 pcs. 2.250.00
10 MM D. BAR 10 pcs. 1,150.00
TIE WIRE #16 5 kgs. 300.00
PORTLAND CEMENT 20 bags 4,160.00
SAHARA 20 Plastic Bag 600.00
ORD. PLYWOOD ¼ 15 sheets 3,750.00
COCO LUMBER 2X2X12 36 pcs. 1,980.00
COCO LUMBER 2X3X12 9 pcs. 675.00
COMMON NAIL #4 4 kgs. 300.00
COMMON NAIL #2½ 4 kgs. 300.00
COMMON NAIL #1½ 2 kgs. 140.00
TOTAL P15,875.00
Proposed Speakers for the Completion of Sound System Project
JBL Equipment:
JBL Control Monitor speaker series with mounting – 3 pairs – 19,980.00 – 59,940.00
Nutrik Mic pro. connector (USA) – 4 pcs. – 230.00 – 920.00
Nobelle Mic cable – 30 meters – 85.00/meter – 2,550.00
Neutrik Pro XLR connector – 4 – 230.00 – 920.00
Neutrik Pro S mount connector – 2 – 180.00 – 360.00
Mounting screw JBL – 16 – 25.00 – 400.00
Local Purchase:
Staple wire, cable ties, Tox screw etc. accs. – 200.00
P65.290.00
Optional:
AVR-UPS configured for PA 5 hrs. (USA) – 1 – 26,380.00
Add:
Shipment cost – 1,800.00
Labor cost – 900.00
Maximum Project Cost – P67,990.00